Bristow's Broad Run VRE Station Is Moving. Where Does the Project Stand This Winter?

The last stop on the Manassas Line is 10637 Piper Lane, between Manassas Regional Airport and the rail yard where VRE parks its trains overnight. Behind it is the Broad Run Maintenance and Storage Facility, and that yard is the reason the station is about to change.

VRE's Broad Run Expansion project page lists construction from December 1, 2026 through February 28, 2029, at a posted cost of $100,133,891. That start date is less than three weeks away. The same page's latest update, dated October 9, says property acquisitions with the City of Manassas and Prince William County are still in progress, and that permits and construction procurement come after those acquisitions close. If you board at Broad Run, the most useful date on that page is when the land is secured, not December 1.

The station moves because the yard needs its ground

VRE states the project's purpose plainly. It will "increase the storage capacity at the Maintenance and Storage Facility (MSF) to receive the additional rolling stock that is currently on order to increase the VRE fleet," and the larger yard "will necessitate reconstruction of the existing station and parking Facilities." The new platform comes as a consequence of the bigger yard.

Here is what the project includes, drawn from VRE's project page and Northern Virginia Transportation Commission meeting materials from September 2025:

  1. Four new storage tracks, plus longer versions of seven of the yard's eight existing tracks.
  2. A reconstructed station platform, shifted east of where it sits today to make room for the larger yard.
  3. A new 6,200-square-foot Administrative and Employee Welfare building with locker rooms, conference rooms, offices and a break area for train crews, maintenance staff and security personnel. It replaces two smaller buildings that will be torn down to make way for the storage tracks.
  4. A new train wash building, added inside the maintenance facility.
  5. Rebuilt station parking, because the expanded footprint takes in ground the current station and lots occupy.

Some of the land work is already on the books. The September 2025 NVTC materials proposed a permanent easement from WilTel Communications, a Lumen Technologies subsidiary, covering approximately 8,200 square feet along the maintenance facility's southwest boundary. That land is needed to build and maintain a retaining wall for slope stabilization, at a price of $204,300 paid from VRE capital funds. A retaining-wall easement that small shows how closely the yard's new edge is being fitted to the parcels around it.

The posted calendar against the latest update

The project page shows a schedule and, below it, a running log of updates. The two don't line up.

Phase Posted start Posted finish Status in VRE's October 9, 2026 update
Development 7/13/2015 9/10/2020 Complete
Property acquisition 11/7/2019 4/1/2026 Still underway with the City of Manassas and Prince William County
Final design 8/10/2021 7/1/2026 Listed as the current phase
Construction 12/1/2026 2/28/2029 Permits and construction procurement to follow acquisitions

The acquisition phase was scheduled to finish in April. The final design phase was scheduled to finish in July. As of early November, the page still lists final design as the current phase.

Work has continued in the meantime. The October 9 update says the team has started reviewing shop drawings for the rail turnouts in an advanced procurement package. Turnouts are the track switches that will feed the new storage tracks. The August 31 update describes an August 21 coordination meeting with the City of Manassas and Prince William County. Both are Authorities Having Jurisdiction for the project, so permits run through two local governments. That meeting covered outstanding review comments and the joint approvals the project needs.

The sequence on VRE's page is acquisitions, then permits, then construction procurement, then construction. As of October 9 the project was still on the first of those steps.

The airport lot runs on a one-year lease

Part of Broad Run's parking already sits on borrowed ground. In 2003, VRE received money from the Governor's Congestion Relief Program for parking expansion at the Manassas and Broad Run stations. The land it chose, at the end of the Broad Run platform, belongs to Manassas Regional Airport. In February 2005, VRE signed a lease with the City of Manassas, which owns the airport, and built 81 parking spaces on the 34,022-square-foot parcel. The lease signed in December 2014 ran through November 2019 and has been renewed one year at a time since then, with rent rising 3 percent each year.

On October 17, 2025, the VRE Operations Board voted 11 to 0 to recommend another 12-month extension at $25,217. The staff memo explained that "this property is likely to be impacted by the VRE Broad Run Expansion project," and that the one-year term would allow more time for talks with the City of Manassas about the land the project needs. The previous extension expired November 30, 2025, so a 12-month extension would reach the end of this November, the day before VRE's posted construction start.

For scale, VRE's live parking page showed 1,018 spaces available at Broad Run on the evening of November 5. The airport lot is a small share of the station's parking, but its lease is one of the clearest records of how the project's land talks are going.

Why the line still ends at Piper Lane

Broad Run is the end of the line because of an earlier decision. The VRE Operations Board once studied extending the Manassas Line 11 miles west, with as many as five new stations, including two in Gainesville and a final stop in Haymarket. The Prince William Times reported that the study put the full extension at $660 million or more in capital costs alone. It projected 6,240 added riders by 2040, only 1,110 more than the 5,130 projected for the Broad Run yard and station option, which was then estimated at about $345 million.

The board voted unanimously to carry only the Broad Run option forward. Marty Nohe, who served on both the Prince William Board of County Supervisors and the VRE Operations Board, told the Prince William Times that "Prince William County is not walking away from Gainesville or even Haymarket as a future expansion," and that "there's a need for additional trains in the corridor right now." The same report said the study expected a bigger Broad Run yard to raise daily trains to and from Union Station from 16 to 22 and shorten the gap between trains from 30 minutes to 20.

The expansion now heading toward construction grew out of that vote. Choosing the cheaper option was supposed to deliver more trains sooner. The land acquisitions show that the cheaper option still has to be fitted around an airport, a fiber easement and two local governments.

What Manassas Line riders are already adjusting to

The rail network east of Bristow is changing too. The Virginia Passenger Rail Authority's Long Bridge project started construction work windows on January 12, 2026. They are expected to continue until the project is finished in 2030. VRE's Long Bridge rider page lists the Manassas Line changes in effect:

  • Trains 332 and 334 end at Alexandria in the morning. Riders can transfer to Metro's Yellow Line, and the Metro fare is paid separately.
  • Train 325 leaves Union Station at 1:00 p.m.
  • Train 327 leaves Union Station at 3:20 p.m. and also carries Fredericksburg passengers, who transfer at Alexandria.
  • Train 331 leaves Union Station at 5:10 p.m. and carries Fredericksburg passengers to the same transfer.

VRE says no trains have been cut and that these adjustments are temporary and "may evolve between 2026 and 2030 as construction progresses."

Weekend trains depend on the same projects. On Sunday, August 23, VRE ran a one-day service for the Freedom 250 Grand Prix in Washington. VRE's announcement said regular weekend service "is currently set to begin upon completion of several rail infrastructure projects" funded through the Transforming Rail in Virginia program, including the Long Bridge expansion. The bridge over the Potomac and the yard behind Broad Run are both part of how VRE plans to add service, and both are on multiyear schedules that end around the turn of the decade.

For now, the best way to track the Bristow end of the line is the update log at the bottom of VRE's Broad Run Expansion page. Construction procurement can begin once an update reports that the acquisitions with the City of Manassas and Prince William County are complete and permits are in hand.

If you live near the Piper Lane end of the line and want to know how a station project like this tends to show up in nearby home values, I'm glad to go through it with you. I'm Andrew Capuano, a Bristow-based REALTOR® and Certified Residential Appraiser, and you can reach me at Andrew R Capuano. Let's Connect.